Development Updates
Update TitleDescriptionDate
15/09/2011China Petroleum Engineering & Construction Corporation (CPECC) awarded $125 million upgrade to add a unit to increase water capacity by 1.3 million barrels per day. Tefken Construction appointed project management consultant for the project.03/07/2019
26/04/2015Upgrade project completed03/07/2019
03/07/2019BP announce potential for further upgrade project to increase water capacity again with additional water required for production and no progress on the CSSP project to provide a water pipeline from the sea to aid oil production at numerous oil fields.03/07/2019